What to Expect
Phase 1
Early Works
COMPLETE
- Constructed the Harmon Channel concrete drainage box culvert to accommodate the future widening of I-15
- Completed drainage and utility work
Phase 2
Tropicana Northside
COMPLETE
- Demolished of the north half of the Tropicana bridge over I-15 and Frank Sinatra Drive
- Constructed the Tropicana Bridge over Dean Martin Drive
- Completed the partial reconstruction of the southbound I-15 to eastbound Tropicana Avenue flyover bridge
Phase 3
Tropicana Southside
ONGOING – February 2025
Improvements to the south side of Tropicana Avenue in preparation for the reopening of the I-15/Tropicana flyover
Demolition of the south half of the Tropicana bridge over I-15 and Frank Sinatra Drive
Reconstruction of bridges over I-15, Frank Sinatra and Dean Martin Drive
Phase 4
Dean Martin Dr
ONGOING – February 2025
Dean Martin Dr connection under Tropicana
Lane Restrictions:
- Dean Martin
Phase 5
Tropicana Ave
February 2025 – late 2025
Improvements to the west side of Tropicana Ave to enhance traffic operations and increase roadway capacity
Lane Restrictions:
- Tropicana Ave